Buffel Park Construction Village

Client

BM Alliance Coal Operations Pty Ltd

Location

Caval Ridge Mine, Moranbah, QLD

Contract

Construct

Contract Value

$109M

Start Date

February 2012

Completion Date

June 2013
showing location on a map of Australia

Decmil was awarded the contract for construction, installation and commissioning of the 1,380 bed village, including all site development works and service infrastructure to house the Caval Ridge Coal Project construction workforce.

Works included ensuite accommodation rooms, dining facilities, laundry, training room, wet mess and recreation facilities. 450 car parks, 10 bus parking bays and a bus stop was constructed.

The project also involved sediment and erosion works, water and waste water treatment plants (capacity for up to 2,500 people), 4km of footpaths and excavation and off-site disposal.

During the project 11,000m3 of concrete was poured and 21km of trenching was delivered, equivalent to 88,000 m3.

Delivering solutions.

We are committed to outstanding project management and delivery regardless of the scale or the intricacy of the work.