Port Hedland Sports and Community Hub

Construction of a new community centre for the Town of Port Hedland.

showing location on a map of Australia

Client

Town of Port Hedland

Location

Port Hedland, Western Australia

Contract

Construct Only

Contract Value

$18M

Start Date

January 2022

Completion Date

May 2023

Decmil was awarded the contract for the Stage 1 construction of the new Port Hedland Sport and Community Hub Centre. Stage 1 consists of three (3) separable portions, including a new community centre, carpark, internal roads, stables refurbishment, landscaping and surrounds.

With the location of the Community Centre close to the horse race track, the work will be undertaken in three (3) separable portions to ensure the uninterrupted running of the 2022 and 2023 horse racing seasons.

  • Separable Portion 1: Demolition, Retaining, Bulk Earthworks and Services: Demolition of existing turf club buildings and surround structures, construction of retaining walls stairs and ramps, installation of internal swales and associated drainage infrastructure, and upgrading and installation of site services.
  • Separable Portion 2: Building Construction, Carpark, Landscaping and Surrounds: construction of new community building, construction of new carpark, and upper (building) level landscaping and surrounds.
  • Separable Portion 3: Landscaping, Internal Road and Stables Refurbishment: lower (track) level landscaping and surrounds, construction of internal roads, and refurbishment of the stables.

Stage 1 is due to be completed in early 2023 ready for the 2023 horse racing season.