RAAF Learmonth Fuel

Client

Department of Defence

Location

Exmouth, Western Australia

Contract

Design and Construct

Contract Value

$19 Million

Start Date

April 2015

Completion Date

November 2016
showing location on a map of Australia

Decmil Australia was awarded a contract for the design and construction of a new 2.1ML fuel facility at RAAF Base Learmonth.

The scope of works included:

  • 14x 150 kL steel tanks;
  • Concrete bunds;
  • Offloading (3x) and uploading (2x) bays for triple road trails;
  • Pumps and integrated pipework for fuel distribution;
  • Fire water system;
  • Store and ablution;
  • Electrical works;
  • Demolition of existing tanks and remediation of site

Delivering solutions.

We are committed to outstanding project management and delivery regardless of the scale or the intricacy of the work.