Ranger Mine Pit 3 Expansion Non-Process Infrastructure

Our network of quality subcontractors and strategic procurement model enables us to provide significant supply chain value for our clients.

showing location on a map of Australia

Client

Energy Resources of Australia

Location

Jabiru, Northern Territory

Contract

Design and Construct

Contract Value

$9 Million

Completion Date

June 2008

The Ranger Mine and the associated town of Jabiru are approximately 230km east of Darwin, surrounded by the Kakadu National Park.

This project involved the detailed design, supply, installation and commissioning of a new tyre store warehouse, day services building, tray truck repair area, diesel storage tank area with incorporated piping and sewerage treatment plant.

In addition to this new work, Decmil upgraded existing infrastructure including installing a 5 tonne monorail crane, an HV wash down facility and a new oil water separator as well as managing the construction and commissioning of the new mine offices supplied and installed by AUSCO Building Systems.