Taloona Gas Plant Stages 1 and 2

The project achieved 75,000 man hours LTI (lost time injury) free.

showing location on a map of Australia

Client

Origin Energy

Location

80km north of Roma, Queensland

Contract

Lump Sum Fixed Price

Contract Value

$10 Million

Start Date

March 2008

Completion Date

December 2008

Origin Energy CSG Limited is developing the Spring Gully coal bed methane field situated approximately 80km north of Roma, Queensland.

The ongoing development included the construction of a gas processing plant at Taloona. Decmil was contracted to supply all labour, material, tools, plant and equipment required to complete the following works:

  • Supply of all pipes, fittings, consumables and materials for the fabrication of pipe spools
  • Supply, manufacture and site installation of compressor canopy shed, structural steel, access platforms, pipe racks and pipe supports Installation of sound proof doors within the compressor shed
  • Installation of pipe spools, including pig launcher and pig receiver
  • Construction, installation and testing of process and utility piping systems
  • Installation of major equipment including 2 inlet separators, 3 gas compressors, glycol dehydration package, sales gas metering skid, 2 fuel gas heaters, oily water system, 3 air compressors, compressed air receiver, oil storage tanks, dry waste oil tanks, plant water tank and flare tip

The project achieved 75,000 man hours LTI free.